Approving Project Expenses: How to Move Quickly Without Skipping Checks
A practical guide to delegated authority, invoice evidence and exceptions, with a construction payment example.
Civil Engineering Jobs editorial team
Fast decisions start with a complete file
A routine invoice should move quickly once it meets the requirements. “Yes until proven no” is a useful attitude for helping someone complete a request, but a poor rule for releasing money. A better default: approve promptly when the evidence and your authority are clear; otherwise, identify the exact issue and who can resolve it.
Know what you are signing
A purchase approval commits funds. Verifying a claim or invoice confirms facts such as delivery, the amount due and compliance with the applicable terms. Releasing payment may be a separate authority. Check your role, limits and any conflict of interest before you sign. A project manager who confirms that work is complete may still lack the authority to approve payment.
Approve, clarify or escalate
Approve: Match the invoice to the purchase order or contract and evidence of receipt or work performed, as applicable. Check quantities, rates, taxes, prior payments, and required approvals. Record what you checked. For an employee expense, follow the applicable policy and ask for the required itemized receipt and business purpose.
Clarify: Ask for the specific missing evidence, name an owner and set a response time. Route uncontested amounts separately if the contract and applicable rules permit it.
Escalate: Pause release if the amount exceeds your delegation, the request may be a duplicate, a change order lacks authorization, or supplier banking details have changed. Verify banking changes through a known contact channel and follow the organization’s independent verification process. [4]
Example: the progress claim includes an extra
A contractor submits a $48,000 progress claim that includes $6,000 for extra excavation. Field records support the excavation, but there is no approved change order in the file. Record the verified quantities, flag the $6,000 and ask the contract administrator to establish entitlement and the approval route. Do not certify the extra solely because it was performed. Track the applicable invoice and notice deadlines immediately; an internal review does not necessarily stop the clock. In Ontario, the Construction Act sets prompt-payment and notice rules where applicable. [5]
Protect both the project and the approver
Unnecessary delays can hurt cash flow, create disputes and trigger contractual or statutory consequences. Inadequate checks can result in duplicate payments, payment for unauthorized work or fraud. An approver may also have to explain a decision in an audit or dispute. A dated record of what you checked, your authority, the decision and any escalation helps the next person understand what happened. Never share sign-in credentials or split amounts to avoid approval limits.
Build speed into the workflow
Give requesters a one-page checklist, route approvals by delegated limit, and assign a named backup for absences. Where policy permits, standardize checks for complete routine claims and require extra review for higher-risk exceptions. Federal section 34 and National Defence guidance illustrate certification in their own context. Ontario’s directive illustrates rules for designated broader public sector organizations and reimbursable expenses. For your project, follow your own delegation, policies, contract and applicable law. [1–3]