Decision theory for infrastructure choices
List actions, possible states and consequences.
Civil Engineering Jobs editorial team
The method
List actions, possible states and consequences. Expected loss weights consequences by their probabilities. Add explicit service and safety constraints where the decision requires them.
A worked situation
For a fictional culvert, repair now costs $40,000. Waiting costs $10,000 in a dry scenario or $100,000 in a wet one. At 30% wet probability, waiting costs $37,000 in expectation. A small change in probability can reverse the ranking.
Put it to work
Solve for the switching probability, then report any unacceptable service outcomes separately. The switching point is about 33%.