Physical consequences of construction design changes
A design change travels through interfaces.
Civil Engineering Jobs editorial team
The method
A design change travels through interfaces. Trace mass, stiffness, drainage, movements and tolerances before pricing its effects. Review temporary and permanent load paths separately.
A worked situation
Moving a roof drain shifts the low point and can change ponding depth, overflow routes and tributary loads. Revised architectural slopes, pipe elevations and structural checks need to agree.
Put it to work
For one revision, list the affected drawings, assumptions and field work. Record who confirms that each interface still works before the change is released.