Making technical risks visible
A useful risk record identifies the mechanism, evidence, exposure, decision deadline and authority.
Civil Engineering Jobs editorial team
The method
A useful risk record identifies the mechanism, evidence, exposure, decision deadline and authority. Reporting a single colour can obscure a missing investigation or a narrow assumption.
A worked situation
For unexpected seepage in an excavation, summarize where flow increased, what measurements are pending and which planned work depends on the findings.
Put it to work
Replace the colour with a decision statement and identify the field observation that triggers escalation.