Value of information in engineering investigations
A test has decision value when its possible results would change the action.
Civil Engineering Jobs editorial team
The method
A test has decision value when its possible results would change the action. Compare the lowest expected loss now with the expected loss after choosing an action for each possible test result. Subtract test and delay costs.
A worked situation
In an illustrative defect investigation, the best current action has expected cost $60,000. After considering both possible test results and appropriate responses, expected action cost is $43,000. If testing and delay cost $9,000, net value is $8,000.
Put it to work
List what you would do after a positive, negative and inconclusive result. Check how accuracy, delay and safety constraints change the decision.